Circle Drive East will have various closures approaching the Gordie Howe Bridge starting at 7:00 a.m. Monday for catch basin installation work. The project is expected to take 10 days to complete, weather permitting and barring any unforeseen circumstances. Speed reductions and detours will be in place around the work zones, as needed.
Approaching the Gordie Howe Bridge, Circle Drive northbound median lane will be closed; and Circle Drive southbound median lane will be closed.
Ruth Street will be closed between Kelvin and Vernon avenues starting at 8:00 a.m. for catch basin work. The intersection at Ruth Street and McPherson Avenue will also be closed during this work. Detours will be in place. The project is expected to take two days to complete.
Clarence Avenue will be closed between Cascade Street and Wilson Crescent starting at 9:30 a.m. for sanitary sewer work. Detours will be in. The project is expected to take two days to complete.
In all cases, Saskatoon Transit may be affected.